Capacity Curtailment on the CH-IT border for delivery period 24-12-2024
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment due to Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
24-12-2024 00:00 - 01:00 2173 MW
24-12-2024 01:00 - 02:00 2173 MW
24-12-2024 02:00 - 03:00 2173 MW
24-12-2024 03:00 - 04:00 2173 MW
24-12-2024 04:00 - 05:00 2173 MW
24-12-2024 05:00 - 06:00 2173 MW
24-12-2024 06:00 - 07:00 2173 MW
24-12-2024 07:00 - 08:00 2173 MW
24-12-2024 08:00 - 09:00 2497 MW
24-12-2024 09:00 - 10:00 2497 MW
24-12-2024 10:00 - 11:00 2497 MW
24-12-2024 11:00 - 12:00 2497 MW
24-12-2024 12:00 - 13:00 2497 MW
24-12-2024 13:00 - 14:00 2497 MW
24-12-2024 14:00 - 15:00 2497 MW
24-12-2024 15:00 - 16:00 2497 MW
24-12-2024 16:00 - 17:00 2497 MW
24-12-2024 17:00 - 18:00 2497 MW
24-12-2024 18:00 - 19:00 2497 MW
24-12-2024 19:00 - 20:00 2497 MW
24-12-2024 20:00 - 21:00 2173 MW
24-12-2024 21:00 - 22:00 2173 MW
24-12-2024 22:00 - 23:00 2173 MW
24-12-2024 23:00 - 24:00 2173 MW
5. Amount of LTTR remaining after curtailment:
24-12-2024 00:00 - 01:00 1904 MW
24-12-2024 01:00 - 02:00 1904 MW
24-12-2024 02:00 - 03:00 1953 MW
24-12-2024 03:00 - 04:00 2017 MW
24-12-2024 04:00 - 05:00 2017 MW
24-12-2024 05:00 - 06:00 1953 MW
24-12-2024 06:00 - 07:00 1904 MW
24-12-2024 07:00 - 08:00 1994 MW
24-12-2024 08:00 - 09:00 1993 MW
24-12-2024 09:00 - 10:00 1993 MW
24-12-2024 10:00 - 11:00 1993 MW
24-12-2024 11:00 - 12:00 1993 MW
24-12-2024 12:00 - 13:00 1993 MW
24-12-2024 13:00 - 14:00 1993 MW
24-12-2024 14:00 - 15:00 1993 MW
24-12-2024 15:00 - 16:00 1993 MW
24-12-2024 16:00 - 17:00 1993 MW
24-12-2024 17:00 - 18:00 1993 MW
24-12-2024 18:00 - 19:00 1993 MW
24-12-2024 19:00 - 20:00 1993 MW
24-12-2024 20:00 - 21:00 1994 MW
24-12-2024 21:00 - 22:00 1994 MW
24-12-2024 22:00 - 23:00 1994 MW
24-12-2024 23:00 - 24:00 1977 MW