Capacity Curtailment on the CH-IT border for delivery period 07-01-2025
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment due to Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
07-01-2025 00:00 - 01:00 2212 MW
07-01-2025 01:00 - 02:00 2212 MW
07-01-2025 02:00 - 03:00 2212 MW
07-01-2025 03:00 - 04:00 2212 MW
07-01-2025 04:00 - 05:00 2212 MW
07-01-2025 05:00 - 06:00 2212 MW
07-01-2025 06:00 - 07:00 2212 MW
07-01-2025 07:00 - 08:00 2212 MW
07-01-2025 08:00 - 09:00 2709 MW
5. Amount of LTTR remaining after curtailment:
07-01-2025 00:00 - 01:00 1988 MW
07-01-2025 01:00 - 02:00 1988 MW
07-01-2025 02:00 - 03:00 1988 MW
07-01-2025 03:00 - 04:00 1988 MW
07-01-2025 04:00 - 05:00 1988 MW
07-01-2025 05:00 - 06:00 1988 MW
07-01-2025 06:00 - 07:00 1988 MW
07-01-2025 07:00 - 08:00 1988 MW
07-01-2025 08:00 - 09:00 2606 MW