Capacity Curtailment on the CH-IT border for delivery period 10-09-2024
Published:
1. TSO(s):
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
10-09-2024 12:00 - 13:00 2142 MW
10-09-2024 13:00 - 14:00 2142 MW
10-09-2024 14:00 - 15:00 2142 MW
10-09-2024 18:00 - 19:00 2142 MW
10-09-2024 19:00 - 20:00 2142 MW
5. Amount of LTTR remaining after curtailment:
10-09-2024 12:00 - 13:00 1813 MW
10-09-2024 13:00 - 14:00 1813 MW
10-09-2024 14:00 - 15:00 1813 MW
10-09-2024 18:00 - 19:00 1831 MW
10-09-2024 19:00 - 20:00 1831 MW