Capacity Curtailment on the CH-IT border for delivery period 16-05-2025
Published:
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment due to Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
16-05-2025 12:00 - 13:00 2741 MW
16-05-2025 13:00 - 14:00 2741 MW
16-05-2025 14:00 - 15:00 2741 MW
16-05-2025 15:00 - 16:00 2741 MW
16-05-2025 16:00 - 17:00 2741 MW
5. Amount of LTTR remaining after curtailment:
16-05-2025 12:00 - 13:00 2640 MW
16-05-2025 13:00 - 14:00 2640 MW
16-05-2025 14:00 - 15:00 2640 MW
16-05-2025 15:00 - 16:00 2640 MW
16-05-2025 16:00 - 17:00 2640 MW