Capacity Curtailment on the CH-IT border for delivery period 27-07-2025
Published:
1. TSO(s)*:
SWISSGRID
2. Identification of affected Long Term Transmission Rights:
CH-IT
3. Triggering event:
Curtailment due to Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
27-07-2025 11:00 - 12:00 1595 MW
27-07-2025 12:00 - 13:00 1595 MW
27-07-2025 13:00 - 14:00 1595 MW
27-07-2025 14:00 - 15:00 1595 MW
5. Amount of LTTR remaining after curtailment:
27-07-2025 11:00 - 12:00 914 MW
27-07-2025 12:00 - 13:00 914 MW
27-07-2025 13:00 - 14:00 914 MW
27-07-2025 14:00 - 15:00 914 MW