Capacity Curtailment on the CH-IT border for delivery period 13-09-2024

Published:

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment due to ensure operation remains within Operational Security Limits.

4. Affected volume in MW / hour for each concerned period:

13-09-2024 12:00 - 13:00 2142 MW

13-09-2024 13:00 - 14:00 2142 MW

13-09-2024 14:00 - 15:00 2142 MW

13-09-2024 18:00 - 19:00 2142 MW

13-09-2024 19:00 - 20:00 2142 MW

5. Amount of LTTR remaining after curtailment:

13-09-2024 12:00 - 13:00 1961 MW

13-09-2024 13:00 - 14:00 1961 MW

13-09-2024 14:00 - 15:00 1961 MW

13-09-2024 18:00 - 19:00 1831 MW

13-09-2024 19:00 - 20:00 1831 MW