Capacity curtailment on the corridors ES-FR, IT<>AT, FR<>IT, AT<>IT, CH<>IT, IT<>SI, IT<>GR for BD 04/05

Published:

Capacity Curtailment on the ES-FR border for delivery period 04-05-2025

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

ES-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2025 10:00 - 11:00 1339 MW

04-05-2025 11:00 - 12:00 1339 MW

04-05-2025 12:00 - 13:00 1339 MW

04-05-2025 13:00 - 14:00 1339 MW

04-05-2025 14:00 - 15:00 1339 MW

04-05-2025 15:00 - 16:00 1339 MW

04-05-2025 16:00 - 17:00 1339 MW

04-05-2025 17:00 - 18:00 1339 MW

5. Amount of LTTR remaining after curtailment:

04-05-2025 10:00 - 11:00 967 MW

04-05-2025 11:00 - 12:00 967 MW

04-05-2025 12:00 - 13:00 967 MW

04-05-2025 13:00 - 14:00 967 MW

04-05-2025 14:00 - 15:00 967 MW

04-05-2025 15:00 - 16:00 967 MW

04-05-2025 16:00 - 17:00 967 MW

04-05-2025 17:00 - 18:00 967 MW

6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :

   04/05/2025

      10:00-11:00 Niort - val de sevre

      11:00-12:00 Niort - val de sevre

      12:00-13:00 Niort - val de sevre

      13:00-14:00 Niort - val de sevre

      14:00-15:00 Niort - val de sevre

      15:00-16:00 Niort - val de sevre

      16:00-17:00 Niort - val de sevre

      17:00-18:00 Niort - val de sevre

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :

   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits

 

Capacity Curtailment on the AT-IT border for delivery period 04-05-2025

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2025 08:00 - 09:00 71 MW

04-05-2025 09:00 - 10:00 71 MW

04-05-2025 10:00 - 11:00 71 MW

04-05-2025 11:00 - 12:00 71 MW

04-05-2025 12:00 - 13:00 71 MW

04-05-2025 13:00 - 14:00 71 MW

04-05-2025 14:00 - 15:00 71 MW

04-05-2025 15:00 - 16:00 71 MW

04-05-2025 16:00 - 17:00 71 MW

04-05-2025 17:00 - 18:00 71 MW

5. Amount of LTTR remaining after curtailment:

04-05-2025 08:00 - 09:00 50 MW

04-05-2025 09:00 - 10:00 50 MW

04-05-2025 10:00 - 11:00 50 MW

04-05-2025 11:00 - 12:00 50 MW

04-05-2025 12:00 - 13:00 50 MW

04-05-2025 13:00 - 14:00 50 MW

04-05-2025 14:00 - 15:00 50 MW

04-05-2025 15:00 - 16:00 50 MW

04-05-2025 16:00 - 17:00 50 MW

04-05-2025 17:00 - 18:00 50 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication

Capacity Curtailment on the FR-IT border for delivery period 04-05-2025

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights:

FR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2025 08:00 - 09:00 457 MW

04-05-2025 09:00 - 10:00 457 MW

04-05-2025 10:00 - 11:00 457 MW

04-05-2025 11:00 - 12:00 457 MW

04-05-2025 12:00 - 13:00 457 MW

04-05-2025 13:00 - 14:00 457 MW

04-05-2025 14:00 - 15:00 457 MW

04-05-2025 15:00 - 16:00 457 MW

04-05-2025 16:00 - 17:00 457 MW

5. Amount of LTTR remaining after curtailment:

04-05-2025 08:00 - 09:00 24 MW

04-05-2025 09:00 - 10:00 23 MW

04-05-2025 10:00 - 11:00 23 MW

04-05-2025 11:00 - 12:00 23 MW

04-05-2025 12:00 - 13:00 23 MW

04-05-2025 13:00 - 14:00 23 MW

04-05-2025 14:00 - 15:00 23 MW

04-05-2025 15:00 - 16:00 24 MW

04-05-2025 16:00 - 17:00 24 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication

 

Capacity Curtailment on the SI-IT border for delivery period 04-05-2025

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights:

SI-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2025 08:00 - 09:00 38 MW

04-05-2025 09:00 - 10:00 38 MW

04-05-2025 10:00 - 11:00 38 MW

04-05-2025 11:00 - 12:00 38 MW

04-05-2025 12:00 - 13:00 38 MW

04-05-2025 13:00 - 14:00 38 MW

04-05-2025 14:00 - 15:00 38 MW

04-05-2025 15:00 - 16:00 38 MW

04-05-2025 16:00 - 17:00 38 MW

5. Amount of LTTR remaining after curtailment:

04-05-2025 08:00 - 09:00 0 MW

04-05-2025 09:00 - 10:00 1 MW

04-05-2025 10:00 - 11:00 1 MW

04-05-2025 11:00 - 12:00 1 MW

04-05-2025 12:00 - 13:00 1 MW

04-05-2025 13:00 - 14:00 1 MW

04-05-2025 14:00 - 15:00 1 MW

04-05-2025 15:00 - 16:00 0 MW

04-05-2025 16:00 - 17:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication

Capacity Curtailment on the IT-GR border for delivery period 04-05-2025

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights:

IT-GR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2025 00:00 - 01:00 50 MW

04-05-2025 01:00 - 02:00 50 MW

04-05-2025 02:00 - 03:00 50 MW

04-05-2025 03:00 - 04:00 50 MW

04-05-2025 04:00 - 05:00 50 MW

04-05-2025 05:00 - 06:00 50 MW

04-05-2025 06:00 - 07:00 50 MW

04-05-2025 07:00 - 08:00 50 MW

04-05-2025 08:00 - 09:00 50 MW

04-05-2025 09:00 - 10:00 50 MW

04-05-2025 10:00 - 11:00 50 MW

04-05-2025 11:00 - 12:00 50 MW

04-05-2025 12:00 - 13:00 50 MW

04-05-2025 13:00 - 14:00 50 MW

04-05-2025 14:00 - 15:00 50 MW

04-05-2025 15:00 - 16:00 50 MW

04-05-2025 16:00 - 17:00 50 MW

04-05-2025 17:00 - 18:00 50 MW

04-05-2025 18:00 - 19:00 50 MW

04-05-2025 19:00 - 20:00 50 MW

04-05-2025 20:00 - 21:00 50 MW

04-05-2025 21:00 - 22:00 50 MW

04-05-2025 22:00 - 23:00 50 MW

04-05-2025 23:00 - 24:00 50 MW

5. Amount of LTTR remaining after curtailment:

04-05-2025 00:00 - 01:00 0 MW

04-05-2025 01:00 - 02:00 0 MW

04-05-2025 02:00 - 03:00 0 MW

04-05-2025 03:00 - 04:00 0 MW

04-05-2025 04:00 - 05:00 0 MW

04-05-2025 05:00 - 06:00 0 MW

04-05-2025 06:00 - 07:00 0 MW

04-05-2025 07:00 - 08:00 0 MW

04-05-2025 08:00 - 09:00 0 MW

04-05-2025 09:00 - 10:00 0 MW

04-05-2025 10:00 - 11:00 0 MW

04-05-2025 11:00 - 12:00 0 MW

04-05-2025 12:00 - 13:00 0 MW

04-05-2025 13:00 - 14:00 0 MW

04-05-2025 14:00 - 15:00 0 MW

04-05-2025 15:00 - 16:00 0 MW

04-05-2025 16:00 - 17:00 0 MW

04-05-2025 17:00 - 18:00 0 MW

04-05-2025 18:00 - 19:00 0 MW

04-05-2025 19:00 - 20:00 0 MW

04-05-2025 20:00 - 21:00 0 MW

04-05-2025 21:00 - 22:00 0 MW

04-05-2025 22:00 - 23:00 0 MW

04-05-2025 23:00 - 24:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

HVDC cable ARACTHOS – GALATINA
 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation
 

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication

Capacity Curtailment on the GR-IT border for delivery period 04-05-2025

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights:

GR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2025 00:00 - 01:00 50 MW

04-05-2025 01:00 - 02:00 50 MW

04-05-2025 02:00 - 03:00 50 MW

04-05-2025 03:00 - 04:00 50 MW

04-05-2025 04:00 - 05:00 50 MW

04-05-2025 05:00 - 06:00 50 MW

04-05-2025 06:00 - 07:00 50 MW

04-05-2025 07:00 - 08:00 50 MW

04-05-2025 08:00 - 09:00 50 MW

04-05-2025 09:00 - 10:00 50 MW

04-05-2025 10:00 - 11:00 50 MW

04-05-2025 11:00 - 12:00 50 MW

04-05-2025 12:00 - 13:00 50 MW

04-05-2025 13:00 - 14:00 50 MW

04-05-2025 14:00 - 15:00 50 MW

04-05-2025 15:00 - 16:00 50 MW

04-05-2025 16:00 - 17:00 50 MW

04-05-2025 17:00 - 18:00 50 MW

04-05-2025 18:00 - 19:00 50 MW

04-05-2025 19:00 - 20:00 50 MW

04-05-2025 20:00 - 21:00 50 MW

04-05-2025 21:00 - 22:00 50 MW

04-05-2025 22:00 - 23:00 50 MW

04-05-2025 23:00 - 24:00 50 MW

5. Amount of LTTR remaining after curtailment:

04-05-2025 00:00 - 01:00 0 MW

04-05-2025 01:00 - 02:00 0 MW

04-05-2025 02:00 - 03:00 0 MW

04-05-2025 03:00 - 04:00 0 MW

04-05-2025 04:00 - 05:00 0 MW

04-05-2025 05:00 - 06:00 0 MW

04-05-2025 06:00 - 07:00 0 MW

04-05-2025 07:00 - 08:00 0 MW

04-05-2025 08:00 - 09:00 0 MW

04-05-2025 09:00 - 10:00 0 MW

04-05-2025 10:00 - 11:00 0 MW

04-05-2025 11:00 - 12:00 0 MW

04-05-2025 12:00 - 13:00 0 MW

04-05-2025 13:00 - 14:00 0 MW

04-05-2025 14:00 - 15:00 0 MW

04-05-2025 15:00 - 16:00 0 MW

04-05-2025 16:00 - 17:00 0 MW

04-05-2025 17:00 - 18:00 0 MW

04-05-2025 18:00 - 19:00 0 MW

04-05-2025 19:00 - 20:00 0 MW

04-05-2025 20:00 - 21:00 0 MW

04-05-2025 21:00 - 22:00 0 MW

04-05-2025 22:00 - 23:00 0 MW

04-05-2025 23:00 - 24:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

HVDC cable ARACTHOS – GALATINA
 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation
 

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication

Capacity Curtailment on the CH-IT border for delivery period 04-05-2025

1. TSO(s)*:

SWISSGRID

2. Identification of affected Long Term Transmission Rights:

CH-IT

3. Triggering event:

Curtailment due to Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-05-2025 08:00 - 09:00 285 MW

04-05-2025 09:00 - 10:00 285 MW

04-05-2025 10:00 - 11:00 285 MW

04-05-2025 11:00 - 12:00 285 MW

04-05-2025 12:00 - 13:00 285 MW

04-05-2025 13:00 - 14:00 285 MW

04-05-2025 14:00 - 15:00 285 MW

04-05-2025 15:00 - 16:00 285 MW

04-05-2025 16:00 - 17:00 285 MW

5. Amount of LTTR remaining after curtailment:

04-05-2025 08:00 - 09:00 0 MW

04-05-2025 09:00 - 10:00 0 MW

04-05-2025 10:00 - 11:00 0 MW

04-05-2025 11:00 - 12:00 0 MW

04-05-2025 12:00 - 13:00 0 MW

04-05-2025 13:00 - 14:00 0 MW

04-05-2025 14:00 - 15:00 0 MW

04-05-2025 15:00 - 16:00 0 MW

04-05-2025 16:00 - 17:00 0 MW