Capacity Curtailment on the AT-CZ border for delivery date 08-05-2024

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

AT-CZ

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

08-05-2024 11:00 - 12:00 350 MW

08-05-2024 12:00 - 13:00 350 MW

08-05-2024 13:00 - 14:00 350 MW

08-05-2024 14:00 - 15:00 350 MW

08-05-2024 15:00 - 16:00 350 MW

08-05-2024 16:00 - 17:00 350 MW

08-05-2024 22:00 - 23:00 350 MW

08-05-2024 23:00 - 24:00 350 MW

5. Amount of LTTR remaining after curtailment:

08-05-2024 11:00 - 12:00 33 MW

08-05-2024 12:00 - 13:00 33 MW

08-05-2024 13:00 - 14:00 33 MW

08-05-2024 14:00 - 15:00 33 MW

08-05-2024 15:00 - 16:00 33 MW

08-05-2024 16:00 - 17:00 33 MW

08-05-2024 22:00 - 23:00 33 MW

08-05-2024 23:00 - 24:00 33 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication