Capacity Curtailment on the AT-CZ border for delivery period 20-04-2025

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

AT-CZ

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

20-04-2025 07:00 - 08:00 350 MW 

20-04-2025 08:00 - 09:00 350 MW 

20-04-2025 09:00 - 10:00 350 MW 

20-04-2025 10:00 - 11:00 350 MW 

20-04-2025 11:00 - 12:00 350 MW 

20-04-2025 12:00 - 13:00 350 MW 

20-04-2025 13:00 - 14:00 350 MW 

20-04-2025 14:00 - 15:00 350 MW 

20-04-2025 15:00 - 16:00 350 MW 

20-04-2025 16:00 - 17:00 350 MW

5. Amount of LTTR remaining after curtailment:

20-04-2025 07:00 - 08:00 270 MW 

20-04-2025 08:00 - 09:00 200 MW 

20-04-2025 09:00 - 10:00 221 MW 

20-04-2025 10:00 - 11:00 223 MW 

20-04-2025 11:00 - 12:00 241 MW 

20-04-2025 12:00 - 13:00 223 MW 

20-04-2025 13:00 - 14:00 223 MW 

20-04-2025 14:00 - 15:00 207 MW 

20-04-2025 15:00 - 16:00 269 MW 

20-04-2025 16:00 - 17:00 269 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication