Capacity Curtailment on D1<>D2 for market period 24, 25, 26 and 27/06/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 24, 25, 26 and 27/06/2019 on the corridor between Denmark 1 and Denmark 2 have been curtailed to ensure operation remains within Operational Security Limits.

24/06/2019 - D1>D2 and D2>D1
On positions 7 it was reduced to 250 MW

25/06/2019 - D1>D2 and D2>D1
From position 17 to position 20 it was reduced to 250 MW

26/06/2019 - D1>D2 and D2>D1
On positions 7 it was reduced to 250 MW

27/06/2019 - D1>D2 and D2>D1
From position 17 to position 20 it was reduced to 250 MW

Best regards,

JAO, Operations Team