Capacity Curtailment on the D2-DE border for delivery 04-10-2023
1. TSO(s)*:
50Hertz
2. Identification of affected Long Term Transmission Rights:
D2-DE
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
04-10-2023 09:00 - 10:00 250 MW
04-10-2023 10:00 - 11:00 250 MW
04-10-2023 11:00 - 12:00 250 MW
04-10-2023 12:00 - 13:00 250 MW
04-10-2023 13:00 - 14:00 250 MW
04-10-2023 14:00 - 15:00 250 MW
5. Amount of LTTR remaining after curtailment:
04-10-2023 09:00 - 10:00 32 MW
04-10-2023 10:00 - 11:00 32 MW
04-10-2023 11:00 - 12:00 32 MW
04-10-2023 12:00 - 13:00 32 MW
04-10-2023 13:00 - 14:00 32 MW
04-10-2023 14:00 - 15:00 32 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Due to the planned outage of Converter KONTEK the maximum transmission capacity of the interconnectors on the border DE/LU – DK2 is limited due to the thermal capacity of the remaining grid elements.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
Due to the planned outage of Converter KONTEK the maximum transmission capacity of the interconnectors on the border DE/LU – DK2 is limited due to the thermal capacity of the remaining grid elements.