Capacity Curtailment on the D2-DE border for delivery date 06-06-2024
1. TSO(s)*:
50Hertz and Energinet
2. Identification of affected Long Term Transmission Rights:
D2-DE
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
06-06-2024 07:00 - 08:00 250 MW
06-06-2024 08:00 - 09:00 250 MW
06-06-2024 09:00 - 10:00 250 MW
06-06-2024 10:00 - 11:00 250 MW
06-06-2024 11:00 - 12:00 250 MW
06-06-2024 12:00 - 13:00 250 MW
06-06-2024 13:00 - 14:00 250 MW
06-06-2024 14:00 - 15:00 250 MW
5. Amount of LTTR remaining after curtailment:
06-06-2024 07:00 - 08:00 53 MW
06-06-2024 08:00 - 09:00 53 MW
06-06-2024 09:00 - 10:00 53 MW
06-06-2024 10:00 - 11:00 53 MW
06-06-2024 11:00 - 12:00 53 MW
06-06-2024 12:00 - 13:00 53 MW
06-06-2024 13:00 - 14:00 53 MW
06-06-2024 14:00 - 15:00 53 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
There is no alternative to the curtailment of the affected LTTRs.
Due to the planned outage of the Kontek Cable the maximum transmission capacity of the interconnectors on the border DE/LU – DK2 is limited due to the thermal capacity of the remaining grid elements.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
There is no alternative to the curtailment of the affected LTTRs.
Due to the planned outage of the Kontek Cable the maximum transmission capacity of the interconnectors on the border DE/LU – DK2 is limited due to the thermal capacity of the remaining grid elements.