Capacity Curtailment on the AT-DE border for delivery period 16-06-2025

Published:

1. TSO(s)*:
APG

2. Identification of affected Long Term Transmission Rights:
AT-DE

3. Triggering event :
Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period :
• 06/16/2025
      • 09:00 - 09:15 463MW
      • 09:15 - 09:30 463MW
      • 09:30 - 09:45 463MW
      • 09:45 - 10:00 463MW
      • 10:00 - 10:15 416MW
      • 10:15 - 10:30 416MW
      • 10:30 - 10:45 416MW
      • 10:45 - 11:00 416MW
      • 11:00 - 11:15 1251MW
      • 11:15 - 11:30 1251MW
      • 11:30 - 11:45 1251MW
      • 11:45 - 12:00 1251MW
      • 12:00 - 12:15 1171MW
      • 12:15 - 12:30 1171MW
      • 12:30 - 12:45 1171MW
      • 12:45 - 13:00 1171MW
      • 13:00 - 13:15 1312MW
      • 13:15 - 13:30 1312MW
      • 13:30 - 13:45 1312MW
      • 13:45 - 14:00 1312MW
      • 14:00 - 14:15 1593MW
      • 14:15 - 14:30 1593MW
      • 14:30 - 14:45 1593MW
      • 14:45 - 15:00 1593MW
      • 15:00 - 15:15 1592MW
      • 15:15 - 15:30 1592MW
      • 15:30 - 15:45 1592MW
      • 15:45 - 16:00 1592MW

5. Amount of LTTR remaining after curtailment:


6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication