Capacity Curtailment on the AT-DE border for delivery period 17-04-2025
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
AT-DE
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
17-04-2025 08:00 - 09:00 3205 MW
17-04-2025 09:00 - 10:00 3205 MW
17-04-2025 10:00 - 11:00 3205 MW
17-04-2025 11:00 - 12:00 3205 MW
17-04-2025 12:00 - 13:00 3205 MW
17-04-2025 13:00 - 14:00 3205 MW
17-04-2025 14:00 - 15:00 3205 MW
17-04-2025 15:00 - 16:00 3205 MW
17-04-2025 16:00 - 17:00 3205 MW
5. Amount of LTTR remaining after curtailment:
17-04-2025 08:00 - 09:00 1542 MW
17-04-2025 09:00 - 10:00 1542 MW
17-04-2025 10:00 - 11:00 1542 MW
17-04-2025 11:00 - 12:00 1542 MW
17-04-2025 12:00 - 13:00 1542 MW
17-04-2025 13:00 - 14:00 1542 MW
17-04-2025 14:00 - 15:00 1542 MW
17-04-2025 15:00 - 16:00 1542 MW
17-04-2025 16:00 - 17:00 1542 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.