Capacity Curtailment on the AT-DE border for delivery period 19-10-2024

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

AT-DE

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

19-10-2024 01:00 - 02:00 3930 MW

19-10-2024 02:00 - 03:00 3930 MW

19-10-2024 03:00 - 04:00 3930 MW

19-10-2024 04:00 - 05:00 3930 MW

19-10-2024 05:00 - 06:00 3930 MW

19-10-2024 08:00 - 09:00 3930 MW

19-10-2024 09:00 - 10:00 3930 MW

19-10-2024 10:00 - 11:00 3930 MW

19-10-2024 11:00 - 12:00 3930 MW

19-10-2024 12:00 - 13:00 3930 MW

19-10-2024 13:00 - 14:00 3930 MW

5. Amount of LTTR remaining after curtailment:

19-10-2024 01:00 - 02:00 3603 MW

19-10-2024 02:00 - 03:00 3528 MW

19-10-2024 03:00 - 04:00 3456 MW

19-10-2024 04:00 - 05:00 3399 MW

19-10-2024 05:00 - 06:00 3656 MW

19-10-2024 08:00 - 09:00 3331 MW

19-10-2024 09:00 - 10:00 3656 MW

19-10-2024 10:00 - 11:00 2379 MW

19-10-2024 11:00 - 12:00 2026 MW

19-10-2024 12:00 - 13:00 1963 MW

19-10-2024 13:00 - 14:00 1783 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.