Capacity Curtailment on the DE-AT border for delivery period 30-03-2025

Published:

1. TSO(s)*:

APG

 

2. Identification of affected Long Term Transmission Rights:

DE-AT

 

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

 

4. Affected volume in MW / hour for each concerned period:

30-03-2025 00:00 - 01:00 4820 MW 

30-03-2025 01:00 - 02:00 4820 MW 

30-03-2025 03:00 - 04:00 4820 MW 

30-03-2025 04:00 - 05:00 4820 MW 

30-03-2025 05:00 - 06:00 4820 MW 

30-03-2025 06:00 - 07:00 4820 MW 

30-03-2025 07:00 - 08:00 4820 MW 

30-03-2025 08:00 - 09:00 4820 MW 

30-03-2025 09:00 - 10:00 4820 MW 

30-03-2025 10:00 - 11:00 4820 MW 

30-03-2025 11:00 - 12:00 4820 MW 

30-03-2025 12:00 - 13:00 4820 MW 

30-03-2025 13:00 - 14:00 4820 MW 

30-03-2025 14:00 - 15:00 4820 MW 

30-03-2025 15:00 - 16:00 4820 MW 

30-03-2025 16:00 - 17:00 4820 MW 

30-03-2025 17:00 - 18:00 4820 MW 

30-03-2025 18:00 - 19:00 4820 MW 

30-03-2025 19:00 - 20:00 4820 MW 

30-03-2025 20:00 - 21:00 4820 MW 

30-03-2025 21:00 - 22:00 4820 MW 

30-03-2025 22:00 - 23:00 4820 MW 

30-03-2025 23:00 - 24:00 4820 MW

 

5. Amount of LTTR remaining after curtailment:

30-03-2025 00:00 - 01:00 4585 MW 

30-03-2025 01:00 - 02:00 4585 MW 

30-03-2025 03:00 - 04:00 4585 MW 

30-03-2025 04:00 - 05:00 4585 MW 

30-03-2025 05:00 - 06:00 4585 MW 

30-03-2025 06:00 - 07:00 4585 MW 

30-03-2025 07:00 - 08:00 4585 MW 

30-03-2025 08:00 - 09:00 4585 MW 

30-03-2025 09:00 - 10:00 4585 MW 

30-03-2025 10:00 - 11:00 4585 MW 

30-03-2025 11:00 - 12:00 4585 MW 

30-03-2025 12:00 - 13:00 4585 MW 

30-03-2025 13:00 - 14:00 4585 MW 

30-03-2025 14:00 - 15:00 4585 MW 

30-03-2025 15:00 - 16:00 4585 MW 

30-03-2025 16:00 - 17:00 4585 MW 

30-03-2025 17:00 - 18:00 4585 MW 

30-03-2025 18:00 - 19:00 4585 MW 

30-03-2025 19:00 - 20:00 4585 MW 

30-03-2025 20:00 - 21:00 4585 MW 

30-03-2025 21:00 - 22:00 4585 MW 

30-03-2025 22:00 - 23:00 4585 MW 

30-03-2025 23:00 - 24:00 4585 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.