Capacity Curtailment on the DE-D1 border for delivery day 29/05/2021

Published:
  1. TSO(s) *:

Energinet              

  1. Identification of affected Long Term Transmission Rights

DE-D1

  1. Triggering event:

 

Curtailment to ensure operation remains within Operational Security Limits

Curtailment due to Force Majeure

Curtailment due to emergency situation

 

  1. Affected volume in MW / hour for each concerned period:

DE-D1: 510 MW Yearly and 340 Monthly from 29-05-2021 08:00 to 29-05-2021 14:00

 

  1. Amount of LTTR remaining after curtailment:

DE-D1: 665 MW from 29-05-2021 08:00 to 29-05-2021 14:00

 

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

There is no alternative to the curtailment of the affected LTTRs.

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

There is no alternative to the curtailment of the affected LTTRs.