Capacity Curtailment from DE-D2 and D2-DE on 3rd and 4th of August

Published:

Dear Market Participants,

Please note that the D2<>DE long-term allocated capacity for market period 03.08.2017 and 04.08.2017 has been curtailed to ensure operation remains within Operational Security Limits.

On 03.08.2017, from position 7 to 24 the capacity has been reduced to 0 MW.

On 04.08.2017, from position 1 to 18 the capacity has been reduced to 0 MW.

Best Regards,

Operations Team