Capacity Curtailment on the DE-NL border for 28th of July
1. TSO(s): TenneT TSO B.V.
2. Identification of affected Long Term Transmission Rights
Germany -> Netherlands
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
28/07/2020:
Germany -> Netherlands:
• 11:00 - 12:00: 1367 MW
• 13:00 - 14:00: 1367 MW
• 14:00 - 15:00: 1367 MW
• 15:00 - 16:00: 1367 MW
5. Amount of LTTR remaining after curtailment :
28/07/2020:
Germany -> Netherlands:
• 11:00 - 12:00: 767 MW
• 13:00 - 14:00: 767 MW
• 14:00 - 15:00: 767 MW
• 15:00 - 16:00: 767 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).
Kind regards,
Gabriele ARNOLDI
Capacity Allocation Specialist