Capacity Curtailment on the DE-NL border for delivery date 07/02/2021

Published:

1.      TSO(s): TenneT TSO B.V.

 

2.      Identification of affected Long Term Transmission Rights

Germany -> Netherlands

 

3.      Triggering event :

 

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

 

4.      Affected volume in MW / hour for each concerned period :

07/02/2021:

Germany -> Netherlands:

00:00 – 01:00  1080 MW
01:00 – 02:00  1080 MW
02:00 – 03:00  1080 MW
03:00 – 04:00  1080 MW
04:00 – 05:00  1080 MW
05:00 – 06:00  1080 MW
06:00 – 07:00  1080 MW
07:00 – 08:00  1080 MW
08:00 – 09:00  1080 MW
09:00 – 10:00  1080 MW
10:00 – 11:00  1080 MW
11:00 – 12:00  1080 MW
12:00 – 13:00  1080 MW
13:00 – 14:00  1080 MW
14:00 – 15:00  1080 MW
15:00 – 16:00  1080 MW
16:00 – 17:00  1080 MW
17:00 – 18:00  1080 MW
18:00 – 19:00  1080 MW
19:00 – 20:00  1080 MW
20:00 – 21:00  1080 MW
21:00 – 22:00  1080 MW
22:00 – 23:00  1080 MW
23:00 – 24:00  1080 MW 

 

5.      Amount of LTTR remaining after curtailment :

07/02/2021:

Germany -> Netherlands:

 

00:00 – 01:00  459 MW

01:00 – 02:00  459 MW

02:00 – 03:00  459 MW

03:00 – 04:00  459 MW

04:00 – 05:00  459 MW

05:00 – 06:00  459 MW

06:00 – 07:00  1080 MW

07:00 – 08:00  1080 MW

08:00 – 09:00  459 MW

09:00 – 10:00  459 MW

10:00 – 11:00  459 MW

11:00 – 12:00  459 MW

12:00 – 13:00  1080 MW

13:00 – 14:00  459 MW

14:00 – 15:00  459 MW

15:00 – 16:00  459 MW

16:00 – 17:00  459 MW

17:00 – 18:00  459 MW

18:00 – 19:00  459 MW

19:00 – 20:00  459 MW

20:00 – 21:00  459 MW

21:00 – 22:00  459 MW

22:00 – 23:00  1080 MW

23:00 – 24:00  459 MW 

 

6.      Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

 

7.      Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).