Capacity Curtailment on the DE-NL border for delivery day 21/10/2021

Published:

1.TSO(s): TenneT TSO B.V.

2.Identification of affected Long Term Transmission Rights

Germany -> Netherlands

3.Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

4.Affected volume in MW / hour for each concerned period :

21/10/2021:

Germany -> Netherlands:
• 01:00 - 02:00: 1080 MW
• 02:00 - 03:00: 1080 MW
• 11:00 - 12:00: 1080 MW
• 14:00 - 15:00: 1080 MW
• 15:00 - 16:00: 1080 MW
• 21:00 - 22:00: 1080 MW
• 22:00 - 23:00: 1080 MW

5.Amount of LTTR remaining after curtailment :

21/10/2021:

Germany -> Netherlands:
                • 01:00 - 02:00: 956 MW
                • 02:00 - 03:00: 985 MW
                • 11:00 - 12:00: 489 MW
                • 14:00 - 15:00: 480 MW
                • 15:00 - 16:00: 499 MW
                • 21:00 - 22:00: 480 MW
                • 22:00 - 23:00: 480 MW

6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).