Capacity Curtailment on the DE-NL border for delivery day 07/01/2022

Published:

1.TSO(s): TenneT TSO B.V.

2.Identification of affected Long Term Transmission Rights

Netherlands -> Germany
Germany -> Netherlands

3.Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

4.Affected volume in MW / hour for each concerned period :

07/01/2022:

Netherlands -> Germany:
• 08:00 - 09:00: 1081 MW
Germany -> Netherlands:
• 00:00 - 01:00: 1081 MW
• 01:00 - 02:00: 1081 MW
• 02:00 - 03:00: 1081 MW
• 03:00 - 04:00: 1081 MW
• 04:00 - 05:00: 1081 MW
• 05:00 - 06:00: 1081 MW

5.Amount of LTTR remaining after curtailment :

07/01/2022:

Netherlands -> Germany:
                • 08:00 - 09:00: 631 MW
Germany -> Netherlands:
                • 00:00 - 01:00: 585 MW
                • 01:00 - 02:00: 590 MW
                • 02:00 - 03:00: 620 MW
                • 03:00 - 04:00: 792 MW
                • 04:00 - 05:00: 787 MW
                • 05:00 - 06:00: 982 MW

6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).