Capacity Curtailment on the DE-NL border for delivery day 09/04/2022
Published:
- TSO(s): TenneT TSO B.V.
- Identification of affected Long Term Transmission Rights
Germany -> Netherlands
- Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period :
09/04/2022:
Germany -> Netherlands:
• 12:00 - 13:00: 1081 MW
• 16:00 - 17:00: 1081 MW
• 17:00 - 18:00: 1081 MW
- Amount of LTTR remaining after curtailment :
09/04/2022:
Germany -> Netherlands:
• 12:00 - 13:00: 481 MW
• 16:00 - 17:00: 849 MW
• 17:00 - 18:00: 825 MW
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).