Capacity Curtailment on the DE-NL border for delivery day 24/05/2020

Published:

1. TSO(s): TenneT TSO B.V.

2. Identification of affected Long Term Transmission Rights

Germany -> Netherlands

3. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period :

24/05/2020:

Germany -> Netherlands:
• 01:00 - 02:00: 1367 MW
• 02:00 - 03:00: 1367 MW
• 03:00 - 04:00: 1367 MW
• 04:00 - 05:00: 1367 MW
• 05:00 - 06:00: 1367 MW
• 06:00 - 07:00: 1367 MW
• 07:00 - 08:00: 1367 MW
• 08:00 - 09:00: 1367 MW
• 09:00 - 10:00: 1367 MW
• 10:00 - 11:00: 1367 MW
• 11:00 - 12:00: 1367 MW
• 12:00 - 13:00: 1367 MW
• 13:00 - 14:00: 1367 MW
• 14:00 - 15:00: 1367 MW
• 15:00 - 16:00: 1367 MW
• 16:00 - 17:00: 1367 MW
• 17:00 - 18:00: 1367 MW
• 18:00 - 19:00: 1367 MW
• 19:00 - 20:00: 1367 MW
• 23:00 - 24:00: 1367 MW

5. Amount of LTTR remaining after curtailment :

24/05/2020:

Germany -> Netherlands:
• 01:00 - 02:00: 1367 MW
• 02:00 - 03:00: 717 MW
• 03:00 - 04:00: 717 MW
• 04:00 - 05:00: 717 MW
• 05:00 - 06:00: 717 MW
• 06:00 - 07:00: 717 MW
• 07:00 - 08:00: 717 MW
• 08:00 - 09:00: 717 MW
• 09:00 - 10:00: 717 MW
• 10:00 - 11:00: 717 MW
• 11:00 - 12:00: 717 MW
• 12:00 - 13:00: 717 MW
• 13:00 - 14:00: 717 MW
• 14:00 - 15:00: 717 MW
• 15:00 - 16:00: 717 MW
• 16:00 - 17:00: 717 MW
• 17:00 - 18:00: 1367 MW
• 18:00 - 19:00: 1367 MW
• 19:00 - 20:00: 1367 MW
• 23:00 - 24:00: 717 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).