Capacity curtailment on the DE-NL border for delivery day 01/05/2020

Published:

1. TSO(s): TenneT TSO B.V.

2. Identification of affected Long Term Transmission Rights

Germany -> Netherlands

3. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period :

01/05/2020:

Germany -> Netherlands:
• 14:00 - 15:00: 1367 MW

5. Amount of LTTR remaining after curtailment :

01/05/2020:

Germany -> Netherlands:
• 14:00 - 15:00: 1069 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment :

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).