Capacity Curtailment on DE-NL border for delivery day 11/10/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 11/10/2019 on corridor from Germany to the Netherlands have been curtailed to ensure operation remains within Operational Security Limits.

DE>NL

On position 4 it was reduced to 1003 MW

From position 12 to 16 it was reduced to 608 MW.

Please consider the latest version of the programming authorizations.

Best regards,

Operations Team

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Image removed.

Attachments
image002.jpg