Capacity Curtailment on the DE-NL border for delivery day 24/04/2021
1. TSO(s): TenneT TSO B.V.
2. Identification of affected Long Term Transmission Rights
Germany -> Netherlands
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
24/04/2021:
Germany -> Netherlands:
• 00:00 - 01:00: 1080 MW
5. Amount of LTTR remaining after curtailment :
24/04/2021:
Germany -> Netherlands:
• 00:00 - 01:00: 480 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).