Capacity Curtailment on the DE-NL border for delivery day 15/05/2021

Published:

1.       TSO(s): TenneT TSO B.V.

 

2.      Identification of affected Long Term Transmission Rights

Germany -> Netherlands

3.       Triggering event :

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4.       Affected volume in MW / hour for each concerned period :

15/05/2021:

Germany -> Netherlands:
• 23:00 - 24:00: 1365 MW

5.       Amount of LTTR remaining after curtailment :

15/05/2021:

Germany -> Netherlands:
                • 23:00 - 24:00: 765 MW

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

 

7.      Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).