Capacity Curtailment on DE-NL border for delivery day 24.05.2021
Published:
- TSO(s): TenneT TSO B.V.
- Identification of affected Long Term Transmission Rights
Germany -> Netherlands
- Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
- Affected volume in MW / hour for each concerned period :
24/05/2021:
Germany -> Netherlands:
• 06:00 - 07:00: 1365 MW
• 09:00 - 10:00: 1365 MW
- Amount of LTTR remaining after curtailment :
24/05/2021:
Germany -> Netherlands:
• 06:00 - 07:00: 1121 MW
• 09:00 - 10:00: 893 MW
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).