Capacity Curtailment on DE-NL border for delivery day 24.05.2021

Published:
  1. TSO(s): TenneT TSO B.V.

 

  1. Identification of affected Long Term Transmission Rights

Germany -> Netherlands

  1. Triggering event :

 

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

  1. Affected volume in MW / hour for each concerned period :

24/05/2021:

Germany -> Netherlands:
• 06:00 - 07:00: 1365 MW
• 09:00 - 10:00: 1365 MW

  1. Amount of LTTR remaining after curtailment :

24/05/2021:

Germany -> Netherlands:
                • 06:00 - 07:00: 1121 MW
                • 09:00 - 10:00: 893 MW

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

 

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).