Capacity Curtailment on the DK-NL and NL-DK border for delivery period 06-05-2025

Published:

1. TSO(s)*:

TenneT TSO B.V.

2. Identification of affected Long Term Transmission Rights:

DK<>NL

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

DK-NL

06-05-2025 07:00 - 08:00 180 MW

06-05-2025 08:00 - 09:00 180 MW

06-05-2025 09:00 - 10:00 180 MW

06-05-2025 10:00 - 11:00 180 MW

06-05-2025 11:00 - 12:00 180 MW

06-05-2025 12:00 - 13:00 180 MW

06-05-2025 13:00 - 14:00 180 MW

06-05-2025 14:00 - 15:00 180 MW

06-05-2025 15:00 - 16:00 180 MW

06-05-2025 16:00 - 17:00 180 MW

06-05-2025 17:00 - 18:00 180 MW

06-05-2025 18:00 - 19:00 180 MW

06-05-2025 19:00 - 20:00 180 MW

06-05-2025 20:00 - 21:00 180 MW

06-05-2025 21:00 - 22:00 180 MW

06-05-2025 22:00 - 23:00 180 MW

06-05-2025 23:00 - 24:00 180 MW

NL-DK

06-05-2025 07:00 - 08:00 180 MW

06-05-2025 08:00 - 09:00 180 MW

06-05-2025 09:00 - 10:00 180 MW

06-05-2025 10:00 - 11:00 180 MW

06-05-2025 11:00 - 12:00 180 MW

06-05-2025 12:00 - 13:00 180 MW

06-05-2025 13:00 - 14:00 180 MW

06-05-2025 14:00 - 15:00 180 MW

06-05-2025 15:00 - 16:00 180 MW

06-05-2025 16:00 - 17:00 180 MW

06-05-2025 17:00 - 18:00 180 MW

06-05-2025 18:00 - 19:00 180 MW

06-05-2025 19:00 - 20:00 180 MW

06-05-2025 20:00 - 21:00 180 MW

06-05-2025 21:00 - 22:00 180 MW

06-05-2025 22:00 - 23:00 180 MW

06-05-2025 23:00 - 24:00 180 MW

5. Amount of LTTR remaining after curtailment:

DK-NL

06-05-2025 07:00 - 08:00 0 MW

06-05-2025 08:00 - 09:00 0 MW

06-05-2025 09:00 - 10:00 0 MW

06-05-2025 10:00 - 11:00 0 MW

06-05-2025 11:00 - 12:00 0 MW

06-05-2025 12:00 - 13:00 0 MW

06-05-2025 13:00 - 14:00 0 MW

06-05-2025 14:00 - 15:00 0 MW

06-05-2025 15:00 - 16:00 0 MW

06-05-2025 16:00 - 17:00 0 MW

06-05-2025 17:00 - 18:00 0 MW

06-05-2025 18:00 - 19:00 0 MW

06-05-2025 19:00 - 20:00 0 MW

06-05-2025 20:00 - 21:00 0 MW

06-05-2025 21:00 - 22:00 0 MW

06-05-2025 22:00 - 23:00 0 MW

06-05-2025 23:00 - 24:00 0 MW

NL-DK

06-05-2025 07:00 - 08:00 0 MW

06-05-2025 08:00 - 09:00 0 MW

06-05-2025 09:00 - 10:00 0 MW

06-05-2025 10:00 - 11:00 0 MW

06-05-2025 11:00 - 12:00 0 MW

06-05-2025 12:00 - 13:00 0 MW

06-05-2025 13:00 - 14:00 0 MW

06-05-2025 14:00 - 15:00 0 MW

06-05-2025 15:00 - 16:00 0 MW

06-05-2025 16:00 - 17:00 0 MW

06-05-2025 17:00 - 18:00 0 MW

06-05-2025 18:00 - 19:00 0 MW

06-05-2025 19:00 - 20:00 0 MW

06-05-2025 20:00 - 21:00 0 MW

06-05-2025 21:00 - 22:00 0 MW

06-05-2025 22:00 - 23:00 0 MW

06-05-2025 23:00 - 24:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

The remedial actions considered were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication