Capacity Curtailment on the DK1-NL border for delivery day 01/02/2020

Published:

TSO(s): TenneT TSO B.V.

Identification of affected Long Term Transmission Rights

Denmark -> Netherlands

Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

Affected volume in MW / hour for each concerned period :

01/02/2020:

Denmark -> Netherlands:
• 00:00 - 23:59: 300 MW

Amount of LTTR remaining after curtailment :

01/02/2020:

Denmark -> Netherlands:
• 00:00 - 23:59: 0 MW

Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).

Operations TEAM