Capacity Curtailment on the DK2<>DE borders for delivery day 30/08/2021
- TSO(s) *:
50Hertz and Energinet
- Identification of affected Long Term Transmission Rights
Year and Month LTTRs
- Triggering event :
Cable outages.
x Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period :
On the border DK2->DE, 32 MW Yearly and Monthly capacities for each hour over the whole curtailment period from 30-08-2021, 06:01 hrs. until 30-08-2021, 24:00 hrs.
On the border DE->DK2, 16 MW Yearly and Monthly capacities for each hour over the whole curtailment period from 30-08-2021, 06:01 hrs. until 30-08-2021, 24:00 hrs.
- Amount of LTTR remaining after curtailment :
On the border DK2->DE: 64 MW
On the border DE->DK2: 80 MW
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
There is no alternative to the curtailment of the affected LTTRs.
Due to the planned outage of Cable the maximum transmission capacity of the interconnectors on the border DE/LU – DK2 is limited due to the thermal capacity of the remaining grid elements.
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
cf. answer to point 6.