Capacity Curtailment on the EE-LV border for delivery period 15-08-2024

Published:

1. TSO(s)*:

ELERING

2. Identification of affected Long Term Transmission Rights:

EE-LV

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

15-08-2024 11:00 - 12:00 465 MW

15-08-2024 12:00 - 13:00 465 MW

15-08-2024 13:00 - 14:00 465 MW

15-08-2024 14:00 - 15:00 465 MW

15-08-2024 15:00 - 16:00 465 MW

15-08-2024 16:00 - 17:00 465 MW

5. Amount of LTTR remaining after curtailment:

15-08-2024 11:00 - 12:00 392 MW

15-08-2024 12:00 - 13:00 392 MW

15-08-2024 13:00 - 14:00 392 MW

15-08-2024 14:00 - 15:00 392 MW

15-08-2024 15:00 - 16:00 392 MW

15-08-2024 16:00 - 17:00 392 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
https://umm.nordpoolgroup.com/#/messages/1ae786be-bf58-4b1f-9dd5-7341022cfabb/24

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?

There is no alternative to the curtailment of the affected LTTRs.