Capacity Curtailment on the EE-LV border for delivery period 24-06-2025
1. TSO(s)*:
ELERING
2. Identification of affected Long Term Transmission Rights:
EE-LV
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
24-06-2025 03:00 - 04:00 500 MW
5. Amount of LTTR remaining after curtailment:
24-06-2025 03:00 - 04:00 465 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication