Capacity Curtailment on the EE-LV border for delivery period 28-11-2025
1. TSO(s)*:
ELERING
2. Identification of affected Long Term Transmission Rights:
EE-LV
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
28-11-2025 00:00 - 01:00 550 MW
28-11-2025 01:00 - 02:00 550 MW
28-11-2025 02:00 - 03:00 550 MW
28-11-2025 03:00 - 04:00 550 MW
28-11-2025 06:00 - 07:00 550 MW
28-11-2025 09:00 - 10:00 550 MW
28-11-2025 10:00 - 11:00 550 MW
28-11-2025 11:00 - 12:00 550 MW
28-11-2025 12:00 - 13:00 550 MW
28-11-2025 13:00 - 14:00 550 MW
28-11-2025 14:00 - 15:00 550 MW
28-11-2025 15:00 - 16:00 550 MW
28-11-2025 16:00 - 17:00 550 MW
28-11-2025 17:00 - 18:00 550 MW
28-11-2025 18:00 - 19:00 550 MW
28-11-2025 21:00 - 22:00 550 MW
5. Amount of LTTR remaining after curtailment:
28-11-2025 00:00 - 01:00 488 MW
28-11-2025 01:00 - 02:00 488 MW
28-11-2025 02:00 - 03:00 488 MW
28-11-2025 03:00 - 04:00 486 MW
28-11-2025 06:00 - 07:00 505 MW
28-11-2025 09:00 - 10:00 509 MW
28-11-2025 10:00 - 11:00 509 MW
28-11-2025 11:00 - 12:00 505 MW
28-11-2025 12:00 - 13:00 505 MW
28-11-2025 13:00 - 14:00 505 MW
28-11-2025 14:00 - 15:00 505 MW
28-11-2025 15:00 - 16:00 505 MW
28-11-2025 16:00 - 17:00 505 MW
28-11-2025 17:00 - 18:00 505 MW
28-11-2025 18:00 - 19:00 505 MW
28-11-2025 21:00 - 22:00 505 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Nord Pool - UMM Platform, as well as the capacity already allocated on the Baltic Balancing Market for balancing capacity sharing at https://baltic.transparency-dashboard.eu/node/108
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
There is no alternative to the curtailment of the affected LTTRs.
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication