Capacity Curtailment on the EE-LV border for delivery period 20/03/2026

Published:

1. TSO(s)*:

ELERING

2. Identification of affected Long Term Transmission Rights:

EE-LV

3, Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / period:

20-03-2026 13:00 - 14:00 449 MW

20-03-2026 14:00 - 15:00 449 MW

20-03-2026 15:00 - 16:00 449 MW

20-03-2026 16:00 - 17:00 449 MW

20-03-2026 17:00 - 18:00 449 MW

20-03-2026 18:00 - 19:00 449 MW

5. Amount of LTTR remaining after curtailment:

20-03-2026 13:00 - 14:00 420 MW

20-03-2026 14:00 - 15:00 409 MW

20-03-2026 15:00 - 16:00 409 MW

20-03-2026 16:00 - 17:00 409 MW

20-03-2026 17:00 - 18:00 409 MW

20-03-2026 18:00 - 19:00 409 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication.