Capacity Curtailment on the EE-LV border for delivery period 12-05-2025

Published:

1. TSO(s)*:

ELERING, AST

2. Identification of affected Long Term Transmission Rights:

EE-LV

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

12-05-2025 03:00 - 04:00 500 MW

5. Amount of LTTR remaining after curtailment:

12-05-2025 03:00 - 04:00 468 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
https://umm.nordpoolgroup.com/#/messages/d2da313f-e46d-4a85-8557-d9e481327115/19
https://baltic.transparency-dashboard.eu/node/108


7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
There is no alternative to the curtailment of the affected LTTRs.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication