Capacity Curtailment on the EL1-GB<>FR border for delivery day 05/08/2022 and 06/08/2022
1.TSO(s) *:
ElecLink
2.Identification of affected Long Term Transmission Rights
ElecLink FR<>GB
3.Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
4.Affected volume in MW / hour for each concerned period :
05/08/2022 and 06/08/2022
§00:00 – 01:00 450MW
§01:00 – 02:00 450MW
§02:00 – 03:00 450MW
§03:00 – 04:00 450MW
§04:00 – 05:00 450MW
§05:00 – 06:00 450MW
§06:00 – 07:00 450MW
§07:00 – 08:00 450MW
§08:00 – 09:00 450MW
§09:00 – 10:00 450MW
§10:00 – 11:00 450MW
§11:00 – 12:00 450MW
§12:00 – 13:00 450MW
§13:00 – 14:00 450MW
§14:00 – 15:00 450MW
§15:00 – 16:00 450MW
§16:00 – 17:00 450MW
§17:00 – 18:00 450MW
§18:00 – 19:00 450MW
§19:00 – 20:00 450MW
§20:00 – 21:00 450MW
§21:00 – 22:00 450MW
§22:00 – 23:00 450MW
§23:00 – 24:00 450MW
5.Amount of LTTR remaining after curtailment :
05/08/2022 and 06/08/2022
§00:00 – 01:00 0MW
§01:00 – 02:00 0MW
§02:00 – 03:00 0MW
§03:00 – 04:00 0MW
§04:00 – 05:00 0MW
§05:00 – 06:00 0MW
§06:00 – 07:00 0MW
§07:00 – 08:00 0MW
§08:00 – 09:00 0MW
§09:00 – 10:00 0MW
§10:00 – 11:00 0MW
§11:00 – 12:00 0MW
§12:00 – 13:00 0MW
§13:00 – 14:00 0MW
§14:00 – 15:00 0MW
§15:00 – 16:00 0MW
§16:00 – 17:00 0MW
§17:00 – 18:00 0MW
§18:00 – 19:00 0MW
§19:00 – 20:00 0MW
§20:00 – 21:00 0MW
§21:00 – 22:00 0MW
§22:00 – 23:00 0MW
§23:00 – 24:00 0MW
6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *: