Capacity Curtailment on the ES-FR border for delivery 01-11-2023

Published:

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

ES-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

01-11-2023 18:00 - 19:00 1450 MW

01-11-2023 19:00 - 20:00 1450 MW

01-11-2023 20:00 - 21:00 1450 MW

01-11-2023 21:00 - 22:00 1450 MW

01-11-2023 22:00 - 23:00 1450 MW

01-11-2023 23:00 - 24:00 1450 MW

5. Amount of LTTR remaining after curtailment:

01-11-2023 18:00 - 19:00 1385 MW

01-11-2023 19:00 - 20:00 1385 MW

01-11-2023 20:00 - 21:00 1385 MW

01-11-2023 21:00 - 22:00 1385 MW

01-11-2023 22:00 - 23:00 1385 MW

01-11-2023 23:00 - 24:00 1385 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication