Capacity Curtailment on the ES-FR border for delivery date 23-05-2024

Published:

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

ES-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

23-05-2024 15:00 - 16:00 1640 MW

23-05-2024 16:00 - 17:00 1640 MW

23-05-2024 17:00 - 18:00 1640 MW

5. Amount of LTTR remaining after curtailment:

23-05-2024 15:00 - 16:00 1421 MW

23-05-2024 16:00 - 17:00 1421 MW

23-05-2024 17:00 - 18:00 1421 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

  23/05/2024      15:00-16:00 Network Security       16:00-17:00 Network Security       17:00-18:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits