Capacity Curtailment on the ES-FR border for delivery day 13/04/2022
Published:
Dear Market Participants,
1. TSO(s) : RTE, REE 2. Identification of affected Long Term Transmission Rights ES->FR 3. Triggering event : Curtailment to ensure operation remains within Operational Security Limits 4. Affected volume in MW / hour for each concerned period : 13/04/2022 06:00-07:00 1830.0 MW 07:00-08:00 1830.0 MW 08:00-09:00 1830.0 MW 09:00-10:00 1830.0 MW 10:00-11:00 1830.0 MW 11:00-12:00 1830.0 MW 12:00-13:00 1830.0 MW 13:00-14:00 1830.0 MW 14:00-15:00 1830.0 MW 17:00-18:00 1830.0 MW 18:00-19:00 1830.0 MW 19:00-20:00 1830.0 MW 20:00-21:00 1830.0 MW 21:00-22:00 1830.0 MW 22:00-23:00 1830.0 MW 23:00-24:00 1830.0 MW 5. Amount of LTTR remaining after curtailment : 13/04/2022 06:00-07:00 1350 MW 07:00-08:00 1350 MW 08:00-09:00 1350 MW 09:00-10:00 1350 MW 10:00-11:00 1350 MW 11:00-12:00 1350 MW 12:00-13:00 1800 MW 13:00-14:00 1800 MW 14:00-15:00 1800 MW 17:00-18:00 1800 MW 18:00-19:00 1800 MW 19:00-20:00 1800 MW 20:00-21:00 1800 MW 21:00-22:00 1800 MW 22:00-23:00 1800 MW 23:00-24:00 1800 MW 6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment : 13/04/2022 06:00-07:00 Network Security 07:00-08:00 Network Security 08:00-09:00 Network Security 09:00-10:00 Network Security 10:00-11:00 Network Security 11:00-12:00 Network Security 12:00-13:00 Network Security 13:00-14:00 Network Security 14:00-15:00 Network Security 17:00-18:00 Network Security 18:00-19:00 Network Security 19:00-20:00 Network Security 20:00-21:00 Network Security 21:00-22:00 Network Security 22:00-23:00 Network Security 23:00-24:00 Network Security 7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? : The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits