Capacity Curtailment on the ES-FR border for delivery day 02/10/2021

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 02/10/2021 on the corridor from Spain to France have been curtailed to ensure operation remains within Operational Security Limits.

ES>FR

From position 4 to 7 it was reduced to 1480MW
From position 8 to 11 it was reduced to 835MW
From position 12 to 15 it was reduced to 535MW
From position 16 to 17 it was reduced to 1084MW
From position 18 to 24 it was reduced to 933MW

 

Please consider the latest version of the programming authorizations.

 

Best regards,
Operations Team