Capacity Curtailment on the ES-FR border for delivery day 04/10/2021

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 04/10/2021 on the corridor from Spain to France have been curtailed to ensure operation remains within Operational Security Limits.

ES>FR

From position 3 to 6 it was reduced to 1629 MW
From position 7 to 12 it was reduced to 880 MW
From position 13 to 15 it was reduced to 933 MW
From position 16 to 17 it was reduced to 1180 MW
From position 18 to 24 it was reduced to 535 MW


Please consider the latest version of the programming authorizations.

Best regards,
Operations Team