Capacity Curtailment on the ES-FR border for delivery day 10/10/2021
Published:
Dear Market Participants,
The long-term allocated capacities for delivery date 10/10/2021 on the corridor from Spain to France have been curtailed to ensure operation remains within Operational Security Limits.
ES>FR
From position 1 to 4 it was reduced to 1035 MW
From position 5 to 7 it was reduced to 1134 MW
From position 8 to 12 it was reduced to 780 MW
From position 13 to 15 it was reduced to 976 MW
From position 16 to 17 it was reduced to 1231 MW
From position 18 to 24 it was reduced to 976 MW
Please consider the latest version of the programming authorizations.
Best regards,
Operations Team