Capacity Curtailment on the ES-FR border for delivery day 03/04/2022

Published:
1. TSO(s) :    RTE, REE 2. Identification of affected Long Term Transmission Rights    ES->FR 3. Triggering event :    Curtailment to ensure operation remains within Operational Security Limits 4. Affected volume in MW / hour for each concerned period :    03/04/2022       11:00-12:00 1830.0 MW       12:00-13:00 1830.0 MW       13:00-14:00 1830.0 MW       14:00-15:00 1830.0 MW 5. Amount of LTTR remaining after curtailment :    03/04/2022       11:00-12:00 1800 MW       12:00-13:00 1800 MW       13:00-14:00 1800 MW       14:00-15:00 1800 MW 6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :    03/04/2022       11:00-12:00 Network Security       12:00-13:00 Network Security       13:00-14:00 Network Security       14:00-15:00 Network Security 7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :    The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits