Capacity Curtailment on the ES-FR border for delivery period 27-09-2024
1. TSO(s)*:
RTE-TSO
2. Identification of affected Long Term Transmission Rights:
ES-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
27-09-2024 00:00 - 01:00 1260 MW
27-09-2024 01:00 - 02:00 1260 MW
27-09-2024 02:00 - 03:00 1260 MW
27-09-2024 03:00 - 04:00 1260 MW
5. Amount of LTTR remaining after curtailment:
27-09-2024 00:00 - 01:00 528 MW
27-09-2024 01:00 - 02:00 528 MW
27-09-2024 02:00 - 03:00 528 MW
27-09-2024 03:00 - 04:00 528 MW
6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :
27/09/2024
00:00-01:00 Network Security
01:00-02:00 Network Security
02:00-03:00 Network Security
03:00-04:00 Network Security
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits