Capacity Curtailment on the ES-FR border for delivery period 25-08-2024

Published:

1. TSO(s)*:

RTE-TSO

2. Identification of affected Long Term Transmission Rights:

ES-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

25-08-2024 07:00 - 08:00 1320 MW

25-08-2024 08:00 - 09:00 1320 MW

25-08-2024 09:00 - 10:00 1320 MW

25-08-2024 10:00 - 11:00 1320 MW

5. Amount of LTTR remaining after curtailment:

25-08-2024 07:00 - 08:00 1081 MW

25-08-2024 08:00 - 09:00 1081 MW

25-08-2024 09:00 - 10:00 1081 MW

25-08-2024 10:00 - 11:00 1081 MW

6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :

   25/08/2024

      07:00-08:00 Network Security

      08:00-09:00 Network Security

      09:00-10:00 Network Security

      10:00-11:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :

   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication