Capacity Curtailment on the ES-FR border for delivery period 03-11-2024
1. TSO(s):
RTE, REE
2. Identification of affected Long Term Transmission Rights:
ES-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
03-11-2024 07:00 - 08:00 1860 MW
03-11-2024 08:00 - 09:00 1860 MW
03-11-2024 09:00 - 10:00 1860 MW
03-11-2024 10:00 - 11:00 1860 MW
03-11-2024 11:00 - 12:00 1860 MW
03-11-2024 12:00 - 13:00 1860 MW
03-11-2024 13:00 - 14:00 1860 MW
03-11-2024 14:00 - 15:00 1860 MW
03-11-2024 15:00 - 16:00 1860 MW
03-11-2024 16:00 - 17:00 1860 MW
03-11-2024 17:00 - 18:00 1860 MW
03-11-2024 18:00 - 19:00 1860 MW
5. Amount of LTTR remaining after curtailment:
03-11-2024 07:00 - 08:00 1232 MW
03-11-2024 08:00 - 09:00 1232 MW
03-11-2024 09:00 - 10:00 1232 MW
03-11-2024 10:00 - 11:00 1232 MW
03-11-2024 11:00 - 12:00 733 MW
03-11-2024 12:00 - 13:00 733 MW
03-11-2024 13:00 - 14:00 733 MW
03-11-2024 14:00 - 15:00 733 MW
03-11-2024 15:00 - 16:00 1178 MW
03-11-2024 16:00 - 17:00 1178 MW
03-11-2024 17:00 - 18:00 1178 MW
03-11-2024 18:00 - 19:00 1178 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
03/11/2024
07:00-08:00 Network Security
08:00-09:00 Network Security
09:00-10:00 Network Security
10:00-11:00 Network Security
11:00-12:00 Network Security
12:00-13:00 Network Security
13:00-14:00 Network Security
14:00-15:00 Network Security
15:00-16:00 Network Security
16:00-17:00 Network Security
17:00-18:00 Network Security
18:00-19:00 Network Security
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits