Capacity Curtailment on the ES-FR border for delivery period 29-11-2024
1. TSO(s):
RTE, REE
2. Identification of affected Long Term Transmission Rights:
ES-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
29-11-2024 11:00 - 12:00 690 MW
29-11-2024 12:00 - 13:00 690 MW
29-11-2024 13:00 - 14:00 690 MW
29-11-2024 14:00 - 15:00 690 MW
5. Amount of LTTR remaining after curtailment:
29-11-2024 11:00 - 12:00 438 MW
29-11-2024 12:00 - 13:00 438 MW
29-11-2024 13:00 - 14:00 438 MW
29-11-2024 14:00 - 15:00 438 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
11:00-12:00 Network Security
12:00-13:00 Network Security
13:00-14:00 Network Security
14:00-15:00 Network Security
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits