Capacity Curtailment on the ES-FR border for delivery period 11-12-2024

Published:

1. TSO(s)*:

RTE-TSO

2. Identification of affected Long Term Transmission Rights:

ES-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

11-12-2024 15:00 - 16:00 690 MW

11-12-2024 16:00 - 17:00 690 MW

11-12-2024 17:00 - 18:00 690 MW

5. Amount of LTTR remaining after curtailment:

11-12-2024 15:00 - 16:00 342 MW

11-12-2024 16:00 - 17:00 342 MW

11-12-2024 17:00 - 18:00 342 MW

6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :
   11/12/2024
      15:00-16:00 Network Security
      16:00-17:00 Network Security
      17:00-18:00 Network Security


7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :
   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits